Services

Commissioning Services

Engineers carrying out commissioning engineering for oil & gas projects

Ensuring safe, reliable, and efficient start-up of energy projects.

MCCS International’s commissioning specialists bring over 30 years of global experience from complex energy commissioning projects, international offshore commissioning projects, onshore projects, FPSOs, refineries, petrochemical plants, liquified natural gas terminals and large industrial facilities.

Our proven methodologies guarantee safe start-up, long-term asset reliability and reduced offshore maintenance & downtime.

What Does Plant Commissioning Mean?

Commissioning is the final phase before a facility starts production. It involves energisation and actual process introduction to ensure equipment and systems operate according to design.

Systems Energisation

Critical utility systems are powered on ahead of testing, following strict permit-to-work lockout/tagout, and safety procedures. Tested systems include:

  • Electrical substations like, transformers, MCCs, and switchgears
  • Service, instrument, air, nitrogen, diesel, HVAC systems
  • DCS, ESD, FGS, and PLC control systems
Functional Testing of Equipment

Every piece of equipment must operate under controlled conditions to confirm equipment readiness before final start-up.
MCCS performs:

  • Motors, solo runs
  • Pump and compressor mechanical run tests
  • Heater, boiler, and burner functional tests
  • Valve stroke tests
  • Turbines pre-start checks
  • Safety system verifications
Loop Testing & Communication Verification

Plant commissioning requires full integration between field instruments and control systems, such as:

  • Final loop checks from instruments to DCS
  • Alarm and trip logic testing
  • Shutdown sequences
  • Interlock validation
  • ESD/FGS functionality testing

These systems ensure accurate control, monitoring, and emergency response capability.

Process System Commissioning

Once utilities and safety systems are proven, MCCS commissions process systems like:

  • Flare system readiness
  • Process gas/hydrocarbon introduction
  • Chemical injection start-up
  • Line-up and isolation checks
  • Equipment operation readiness

These ensure that each process unit operates within design parameters.

Safety & Protective Systems Commissioning

The following safety systems are thoroughly validated to ensure personnel and asset protection during operations:

  • Fire & Gas System testing
  • Deluge and sprinkler activation tests
  • Emergency shutdown ESD logic execution
  • Blowdown system operation
  • Pressure relief device validation
  • Emergency lighting & escape route checks
Dynamic Testing

Previous tests to this stage are simulated without oil and gas. The following systems need to be proven to run in real operating conditions:

  • Flow tests
  • Pressure control stability
  • Temperature control response
  • Separator performance testing
  • Compressor/ turbine performance testing
  • Pump NPSH & flow curve checks
Optimisation & Troubleshooting

Few oil and gas, LNG, and energy plants start operating perfectly on the first try. Commissioning tests will often reveal gaps that require targeted fine-tuning to meet the design intent. MCCS delivers:

  • Control loop tuning to stabilise operations
  • Process optimisation to achieve design performance.
  • Equipment vibration analysis for early fault detection.
  • Performance data logging for operational validation
  • Vendor coordination for specialist equipment for equipment-specific issues.
Punch List Closure

The last stage of commissioning before the certificates can be issued is the closing of all remaining B and C punch items, including:

  • Final vendor punch lists
  • Control room action lists
Documentation, Certification & Handover

Once all tests are complete, MCCS hands over full commissioning documentation and certificates. These are:

  • Functional test reports
  • Loop check results
  • Equipment start-up reports
  • As-built P&ID
  • Commissioning dossiers
  • Operations handover package
  • Ready For Start-Up (RFSU) Certificate
  • Operations Training & Briefing
  • Final Punch list closure

The facility is now fully operational and ready for production.

Choose MCCS As Your Plant Commissioning Vendor

With over 30 years of international offshore commissioning experience, MCCS are well-positioned to energise your oil and gas project.

MCCS has had the privilege of serving a diverse portfolio of international clients