Ensuring safe handover from construction to commissioning.
Mechanical completion (MC) is the first major step of pre-commissioning, marking the handover from construction to commissioning. This crucial step must be done with precision and safety.
At MCCS, we have been delivering international mechanical completion and pre commissioning services to plant, renewable, oil and gas clients – across Asia, the Pacific, the Middle East, and Europe and global offshore enviroments for over 30 years.
Mechanical completion ensures that all equipment, piping, instruments, and systems in a facility are fully installed and verified in accordance with engineering design, safety requirements and global construction standards.
Our experienced engineers, supervisors, and technicians manage every aspect of the mechanical completion to pre-commissioning process to prepare your assets for safe commissioning and start-up.
The Stages of Mechanical Completion
The stages of mechanical completion involve the final construction checks, documentation handover, and preparation for pre-commissioning. These are as follows:
Systems and Sub-systems Breakdown
We structure your project into systems and subsystems to streamline execution and documentation.
Our scope includes:
Breaking down the facility into sections (mechanical completion packages).
Defining system boundaries, tags, and discipline ownership.
Prioritisation of packages with commissioning and start-up logic in mind.
This structured approach improves traceability, speeds up approvals and supports efficient handover to the pre-commissioning stage.
Comprehensive Inspection & Verification
MCCS performs detailed inspections to confirm that all equipment and components are installed correctly and ready for testing.
This includes:
Verification of mechanical alignment, piping, supports and structural elements.
Instrument installation and continuity tests.
Electrical tests of continuity, cable megger tests, grounding, etc.
P&IDs conformity checks.
Ensured compliance with international codes and client standards
Our inspection process ensures quality, safety, and full engineering integrity before the system progresses to the pre-commissioning stage.
Static Testing & Verification Activities
MCCS executes all required static tests for quality confirmations to ensure piping, vessels, and equipment integrity in accordance with approved procedures, codes, and project specifications prior to system handover.
Flange management and joint integrity management
Pressure tests, including hydrotesting, pneumatic testing, and nitrogen/helium leak testing.
Pipeline cleaning via flushing, chemical cleaning, nitrogen purging, or air blowing.
Equipment and vessel integrity inspections
These tests ensure your plant is safe, leak-free and reliable.
Punch List Management
Our teams lead and coordinate punch list activities to ensure any issues are identified, logged and closed.
We track progress with our proprietary completion management software, PUMA+, which allows us to:
Categorise punch items into priorities (A, B, and C).
Close critical A-priority punches before handover for facility pre-commissioning.
Ensuring transparency and efficiency in managing punch lists to avoid delays in project timelines.
Inspection Test Records and Certification
This is the formal sign-off of mechanical completion certificates that state that systems are built to specification, have been tested thoroughly, and that the project is ready for pre-commissioning.
We manage all project documents with PUMA+, ensuring the following records and certificates are accurately captured and verified:
Mechanical Completion Certificate
Ready for Commissioning Certificate
Inspection Test Records in accordance with the inspection test plan
QA/QC verification
Witnessing strategy with the client
Handover to Pre-commissioning
Once all activities are completed, we formally certify the system as ready for pre-commissioning. This final stage includes:
Validating documentation and punch item closure
Ensuring system/subsystem readiness
Coordinating with commissioning teams for a smooth transition
Choose MCCS As Your Mechanical Completion Coordinator
Our focus is to handover systems for pre-commissioning, with full transparency, without exceptions. With over 30 years of experience, we are well-positioned to provide a bespoke, quality testing and handover plan for any plant, facility or offshore oil and gas project.